Challenges

This restaurant was forced to shutdown due to a pipe refusing to drain. After visiting the location, we learned that this pipe was located inside their kitchen and required a substantially large area to be excavated, so the plumber could gain access for the repair. Even more challenging was that the dig area was full of clay, plus a variety of concrete slabs and brick.

How We ACE’d It

The ACE Team manipulated the material via hand tools, while our high-powered vacuum truck extracted the soil, clay, concrete slabs and brick from the area. In only 3 days, a 20’ long by 4’ wide by 8’ deep area was vacuum excavated so the repair could be made and the restaurant could resume operations for the much anticipated busy weekend.